Bathrooms · Straight answers from the Alanis family

What order does a bathroom remodel happen in?

Key takeaways

  • The order is not a style preference. It runs demolition, rough plumbing and electrical, inspection, waterproofing, board, tile, paint, fixtures, because the wall cannot close until the city has seen inside it and nothing wet goes on an unsealed surface.
  • Any bathroom that moves a drain, a valve or a fan is a plumbing or electrical project first, and that's what puts a city inspection in the middle of the schedule.
  • In Anna, the permit is step zero. The City of Anna Building Department answers "Is a permit required for a Remodel?" with "Yes, a permit is required," and inspections have to be requested by 4 p.m. the business day before.

The question behind this search is simple: what happens first? What a homeowner really wants to know is when they get their bathroom back, and whether the thing they have not picked yet is about to hold up the whole job. Alanis Remodeling & Construction is a family-owned remodeling company based in Anna, Texas, working across Collin County since 1999. Here's the order a bathroom remodel runs in, and the reason behind each step.

What happens first in a bathroom remodel?

Two things, and neither one is demolition. First, the scope and the drawings get finished and the permit application goes in. Second, your selections get locked and the long-lead items get ordered. Demo is the third thing, and starting it before the other two is how a bathroom sits half finished for three weeks.

The city of Anna's residential remodel checklist explains why the paperwork is first. It asks for two sets of plans, a written scope of work that spells out the plumbing, electrical and mechanical work, the names of the subcontractors doing it, and any walls being added or removed. You cannot write that document after the walls are open. Writing it is what forces every decision into the open while changing your mind is still free.

What are the steps to remodel a bathroom, in order?

Here's the standard sequence for a bathroom, and what each step is waiting on.

  1. Design, scope and written proposal. The layout, the fixture list, and the price and dates in writing.
  2. Permit application. Plans, scope of work and subcontractors go to the city.
  3. Selections and ordering. Tile, vanity, fixtures, shower glass. Long-lead items go first.
  4. Protection and demolition. Floors and doorways covered, old tile, tub, vanity and toilet out, walls opened where the plumbing has to move.
  5. Rough plumbing. Supply and drain lines moved, shower valve set, tub or shower pan drain placed, toilet flange height corrected.
  6. Rough electrical and ventilation. Vanity lights, ceiling light, GFCI outlets, exhaust fan and its duct.
  7. Blocking. Backing for grab bars, a bench, a floating vanity or a glass panel, installed while the wall is open.
  8. Rough-in inspection. The city looks at the plumbing and electrical before anything covers it.
  9. Insulation, waterproofing and board. Vapor and waterproofing layers, cement board in the wet areas, drywall everywhere else.
  10. Tile. Shower walls first, then the floor, then grout and seal.
  11. Paint. Walls and ceiling, before the vanity and trim go back.
  12. Fixtures and finish. Vanity, top, faucets, toilet, lights, exhaust grille, shower glass, mirrors, hardware.
  13. Final inspection and walkthrough. The city signs off, then we walk the room with you.

Steps 4 through 8 are the part people underestimate. That is the stretch where the bathroom is unusable and nothing visible is happening.

Why can't the tile go in before the plumbing?

Because tile is a cover, and covers go on last. Every step in a bathroom either runs something through the wall, closes the wall, or decorates the closed wall, and they only work in that direction. Put tile on a wall with a valve still to move and the wall comes back off.

There are three one-way gates in the sequence:

GateNothing past it untilWhy
Rough-in inspectionThe city has seen the pipe and wireBoard and tile hide the work being inspected
WaterproofingThe wet-area surfaces are sealedTile and grout are not waterproof on their own
FixturesTile is set, grouted and curedA vanity and toilet set on finished surfaces

Blocking belongs in that list too. The CDC advises homeowners to "Add grab bars inside and outside your tub or shower and next to the toilet." Grab bars need wood behind the tile. Decide that at step 3, not step 12.

Planning a bathroom and want the sequence in writing before you commit? Request a free in-home estimate and we will walk your bathroom, tell you whether the plumbing has to move, and hand you the order of work with your dates on it.

Where do the permit and the inspection sit in the order?

The permit sits before demolition and the inspection sits in the middle, right after rough-in. That one inspection is the hinge of the whole schedule, and in Anna it has a cutoff. According to the City of Anna's permit process page, inspection requests go to the city by 4 p.m. the business day before, and none are done on weekends or holidays.

Read that again with a calendar next to it. Rough-in finishing on a Friday afternoon does not get looked at until the following week. The way around it is to finish rough-in midweek, so the request goes in the next day and the wall can close before the weekend. That is not a trick, it is just knowing the rule.

In Anna, start from yes and call the Building Department at 972-924-2616 with your scope. Our post on permits for a remodel in Anna covers the paperwork in full.

Which step is the homeowner's job?

Step 3, and it has a real deadline. The crew can demo, move plumbing and close walls without knowing which vanity you picked. It cannot set tile without the tile, and it cannot order shower glass until the tile is set and measured. Selections that are not done by the end of demolition are one of the reasons a bathroom sits still.

A simple rule: anything that gets tiled against or plumbed to has to be chosen before the wall opens. That means the shower valve trim, the tub or pan, the toilet, the vanity width and the faucet hole spacing. Tile color can wait a few days. Paint can wait weeks. Towel bars can wait until the end.

Is the order different for a tub-to-shower conversion?

The order is the same, but step 5 gets bigger. Trading a tub for a larger walk-in shower means the drain moves, the pan or base is set and sloped, and the waterproofing area grows.

Tub-to-shower conversions, walk-in showers, tile, custom vanities, fixtures and waterproof flooring are all on our bathroom remodeling page, and the framing and drywall around them is our own crew, so steps 7 through 9 stay with one crew instead of waiting on another company.

What happens if they find something inside the wall?

That is step 4 and a half, and it is the step nobody writes about. Opening a wet wall is when you find out whether the last shower leaked: rot in the bottom plate, a subfloor that has gone soft, failed waterproofing behind old tile, or a drain that was never sloped right. None of that is visible at the estimate, which is why no honest estimate pretends otherwise.

What should happen is simple. The crew stops, shows you what it found, and tells you what it does to the price and the dates before going any further. The thing to look for when you are hiring is not a company that promises nothing will be found. It is one that tells you in advance how a find gets handled.

Get the order of work in writing

Book a free in-home estimate. We look at your bathroom, tell you whether the plumbing has to move, explain what Anna or your city will require, and hand you the sequence with your dates and your inspection days on it. The price goes in writing before the work starts.

See finished bathrooms in the project gallery, look at what we handle on the bathroom remodeling page, or request your free estimate. Prefer to talk now? Call (214) 451-7499.

About the author

Angel Alanis is the project manager at Alanis Remodeling & Construction, a family-owned remodeling company in Anna, Texas since 1999. He runs the schedule and the day to day communication on kitchen, bathroom and whole-home projects across Collin County and the Dallas-Fort Worth area. Meet the family.

Questions, answered.

Does paint go on before or after the tile?

After the tile and before the fixtures. Tile work and grout are messy, so painting a finished wall first means touching it up later anyway. Paint once the board and tile are done and before the vanity, toilet and hardware go back in, so you are not cutting in around them.

Can the order change?

The gates cannot. Rough-in before board, inspection before cover, waterproofing before tile, tile before fixtures. What moves is the sequencing inside a step, like whether floor tile goes down before or after the shower walls, and whether painting happens in one pass or two. Ask your crew which choice they are making and why.

How long is the bathroom unusable?

From demolition through tile, which is the whole middle of the list. The length depends on your scope and on the inspection calendar, not on how fast anyone works. Ask for the order of work with dates on it, and look for the rough-in inspection day, because every date after it depends on that one.

What is the last thing that happens?

Shower glass, usually, because it gets measured after the tile is set, and then the final inspection and the walkthrough. We walk every detail with you before we call the job done.

Can we go through the sequence in Spanish?

Yes. The whole family is bilingual, so the walkthrough, the written proposal and every daily update can happen in Spanish or English. Visit our Spanish page or just ask when you call.

Toda la familia habla español.

Visite nuestra página en español
Free Estimate

Get your price
in writing.

Tell us about your project and the Alanis family will schedule your free estimate. Prefer to talk now? Call us.

Free in-home estimate, no obligation
Upfront costs in writing, no hidden fees
Family crew, English and Spanish
Tap to call (214) 451-7499
What happens next
01We call to set a time that works
02Free walkthrough at your home
03Your price and schedule, in writing

$25,000 Guarantee. Every project we take on is backed by The Good Contractors List.

"Whatever your project, big or small, Jesus and Angel should be your 'I know a guy'."

Kyle Stephenson · Google Review

Tell the family about your project

Takes about a minute. The family reads every one.

Free Estimate